Hi Maruti,
As you are aware, task confirmations can be carried out in 3 ways
# | Task confimation method | Pre-Requisite |
---|---|---|
1 | Directly in the project structure | User has to have admin authorisation at project definition or Read access at project definition with write/admin at task level |
2 | Through 'My Tasks' dashboard | User has to have write access at task level (This can be achieved by selecting responsible role in the task or through task to role to BP to user assignment) |
3 | Through CAT2 tcode | No authorisation is required, but task to role to BP to Personnel number assignment is required |
Hope this clarifies your question.
Regards,
Ravi