Hierarchy in IP11 and Tasklist maintenance package

$
0
0

Guys,

 

Good day. I have a question.

 

Assuming that i created a maintenance strategy ABC001 and it has maintenance packages 1M with hirearchy 1 and 4M with hirearchy 2. This means when 4M is due,1M will not happen.

 

Now i am going to create my tasklist with two operations.

 

10. 1M operation checklist

20. 4M operation checklist

 

 

When i create a Tasklist with ABC001 strategy and go into maintenance package tab, i will choose 1M for first operation. If i want the 1M operation also when 4M operation is due, i have to check 1M AND 4M against 4M operation checklist. But this is different that what we did in IP11 for ABC001 package(We are saying 1M will not happen when 4M is due and giving a higher hirearchy)... But the Tasklist i have selected both 1m and 4M package, how will the system react?

 

Please advice.

 

Thanks,

Syl