Hi Muktar,
we donot do the carry forward of capital budget in our company.but as there is no budget system should check the availablity during GRN. Also There is budget available for Rs.2000.But while doing MIRO if the value is more than Rs1 from PO value(eg.Rs.2000) system is asking for budget is exceeded by Rs 2001 but not by Rs.1
Also if PR is created for a capital item in the FY-2013 dated 25.03.2014.While we are creating PO n the FY-2014 for the same PR by giving delivery date as 30.03.2014 system is allowing to do the PO.But if the delivery date is in the FY-2014 e.g.10.04.2014 system is not allowing to do the PO.Is it the normal behavior of the system to check the budget for the same PR in the FY-2014 as the delivery date is in FY-2014 or some other issue is involved.Pl. advice.
Regards,
Shivaji